ISLAMABAD: The National Transmission and Despatch Company Limited (NTDC) has achieved the successful replacement of a 108 km 220 KV transmission line in the south region and energized the newly constructed Guddu-Shikarpur transmission line.
This significant milestone marks a major step towards improving the power supply system in the South areas of Pakistan, specifically Balochistan and Sindh Provinces, said a press release.
Guddu-Shikarpur Transmission Line project has been completed with a total contract cost of USD 13,108,994 and PKR 1,630,460,035, this transformative project addresses operational problems and system bottlenecks that plagued the previous transmission line.
This vital project will strengthen the connection between Guddu and Shikarpur, resulting in improved stability and reliability of the power transmission network.
The existing 220kV Guddu-Sibbi single circuit transmission line, constructed in 1977, suffered from aging and deterioration of the PCC Poles + Steel Towers.
Over the course of its more than 40 years of service, the transmission line experienced a de-rated capacity, causing frequent operational challenges for power transmission from Uch Power Plants to respective load centres.
NTDC, the leading national power transmission company, undertook this project as part of its commitment to enhance the country’s power infrastructure.
By investing in critical upgrades, NTDC aims to address the increasing demand for electricity and ensure a reliable supply to meet the needs of industries, businesses, and households across Pakistan.
The Asian Development Bank’s financial support played a crucial role in the realization of this project. The collaboration between NTDC and ADB exemplifies the commitment of both organizations to sustainable development and the improvement of Pakistan’s power infrastructure.
Managing Director NTDC, Engr. Dr Rana Abdul Jabbar Khan appreciated the Project Delivery South team for their efforts to complete this critical project.